Project Description
The Tir John landfill has fulfilled waste management requirements for residents and commercial contractors in South West Wales since the 1960s. The facility is adjacent to the Crymlyn Bog, which is a designated Special Area of Conservation (SAC). The disposal of residual waste is managed by Swansea City Waste Disposal Company Limited (SCWDCL) who operate the site and the City and County of Swansea required a final capping system design.
The Challenge
In 2012 the Tir John landfill required a permanent geosynthetic capping system and 1m of soil cover.
The requirement was to design a capping solution that would enable fast installation onto this large area. The geosynthetic capping system design called for a high performance geocomposite drainage and protection layer, impermeable geomembrane and gas dispersal geocomposite.
A large proportion of the landfill cap was constructed on very steep slopes where it was necessary to ensure slope stability during construction. The challenge was to produce a cost effective design that resulted in adequate stability on steep slopes, without the use of geogrid reinforcement.
The Solution
The designer worked with ABG to develop a geosynthetic capping solution that would provide the required drainage/gas venting flow capacity and frictional performance to ensure slope stability. ABG’s unique Pozidrain G4SD geocomposite drainage layer with enhanced frictional performance was specified and installed on top of the 1mm LLDPE textured geomembrane for drainage, and below for gas dispersal. Shear box test results for the Pozidrain vs cover soil interface indicated sufficient frictional performance to achieve the required factor of safety for the 50m long 1 in 3 slope installation.
This landfill cap was completed without any stability problems and drainage performance was reported to be as required for the 6ha landfill cap.

ABG Pozidrain G Geocomposite with enhanced frictional properties specifically designed for steep slope installations above and below a capping liner.
The ABG Service
ABG provided design assistance. This included shear box testing, slope stability and flow capacity calculations.